Mitsubishi Pajero

1982-1998 of release

Repair and car operation



Митсубиси Паджеро
+ 1.1. The instrument panel and control means
+ 2. Maintenance service
+ 3. Engines
+ 4. Cooling system
+ 5. Greasing system
+ 6. The power supply system
+ 7. Release system
+ 8. Fuel system
- 9. A running part
   - 9.1. A mechanical transmission
      9.1.1. The mechanism of management of a check point
      9.1.2. The gauge of deenergizing of coupling (1990-98)
      9.1.3. The gear change lever (and / m 4х4)
      9.1.4. The switch of a signal of movement by a backing
      9.1.5. An epiploon of a shaft of a check point (or a leading shaft of a distributing box)
      9.1.6. Removal and check point installation
   + 9.2. Coupling
   + 9.3. Automatic transmission
   + 9.4. The back bridge
+ 10. A suspension bracket and a steering
+ 11. Brake system
+ 12. A body
+ 13. An electric equipment
+ 14. Electroschemes




ccf2698e

9.1.6. Removal and check point installation

THE GENERAL DATA

Transmission and distributing box а/м 1992-98

N – the detail is subject to the obligatory
To replacement at dismantling-assemblage
1. A casing (cover)
2–6. Sockets
7. The gauge of deenergizing of a lobby
Leading axis
8. A speedometer cable
9, 12, 13. A guard
10. The main cylinder
11. A starter
14, 15. A lateral arm
16. A cover картера couplings
17. Торсион check point support
18. An arm
19. 2nd cross-beam
20. A pillow of a back support of the engine
21. An arm of a guard of a distributing box
22. Демпфер
23. A check point with a distributing box
24. The case of a control lever of a check point
25. A lining
And. The sizes and carvings of the bolts specified by letters And, In etc.

Removal and installation

CARS 1983-89

PERFORMANCE ORDER
1. Translate the check point lever in neutral position.
2. Remove the lever of a check point and close an aperture.
3. Disconnect the battery from weight and lift the car.
4. Designate position of flanges карданных shaft and disconnect shaft from a check point.
5. Designate and disconnect from картера a check point all cables and wires, disconnect wires from a starter.
6. Slightly will hang out the engine, having propped up its jack in the pallet through wooden колодку.
7. Remove a distributing box.
8. Remove a starter.
9. Prop up a check point the cart with a jack.
10. Turn on at first bolts картера couplings, then bolts and nuts of fastening of a cross-beam, remove a cross-beam and details of fastening of a cross-beam.
11. Lower a jack of the engine a little and disconnect a check point from the engine, having displaced the cart so that the primary shaft of a check point left coupling.
12. Installation is carried out upside-down.
13. Tighten connections with following moments: bolts картера couplings – 49 Н.м., starter nuts – 27 Н.м., bolts of a distributing box – 12 Н.м.

CARS 1990-98

PERFORMANCE ORDER
1. Translate the check point lever in neutral position.
2. Remove the lever of a check point and close an aperture.
3. Disconnect the battery from weight and lift the car.
4. Remove a guard of a distributing box.
5. Remove a forward exhaust pipe.
6. Merge from a check point oil.
7. Designate position of flanges карданных shaft and disconnect shaft from a check point.
8. Remove a cover from a check point shaft.
9. Designate and disconnect from картера a check point all cables and wires.
10. Remove a guard of the main cylinder of coupling, remove the cylinder, take aside and fix.
11. Remove a starter.
12. Slightly will hang out the engine, having propped up its jack in the pallet through wooden колодку.
13. Prop up a check point the cart with a jack.
14. Disconnect lateral arms from картера a check point.
15. Remove the bottom cover картера couplings.
16. Remove an arm of a distributing box.
17. Turn on at first bolts of fastening of a check point to a cross-beam, raise a check point on 6 mm and remove a cross-beam.
18. Remove a check point with a distributing box.
19. For this purpose turn away bolts and submit a check point towards a back part of the car, having displaced the cart a little.
20. Lower and remove a check point, slightly having inclined a forward part and having submitted forward so that not to touch a back extreme cross-beam.
21. Installation is carried out upside-down.
22. At check point installation on the engine совестите apertures with directing pins, slightly having inclined the engine.